A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

  • A. Identify the path through the schedule with leveled resources and the shortest duration.
  • B. Identify the tasks with float duration, which do not impact the duration of the project.
  • C. Identify the crashed project schedule to find the shortest duration to complete the project.
  • D. Identify the longest activity path in the schedule with the shortest possible duration.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: D
The critical path is the longest sequence of dependent activities from project start to finish that determines the shortest time in which the project can be completed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...