Exam CAPM topic 1 question 379 discussion

Actual exam question from PMI's CAPM
Question #: 379
Topic #: 1
[All CAPM Questions]

A project team has completed the sprint review and the users are impressed by the demo. However, another functionality included in the sprint that was not discussed in the review is not ready for production deployment.

What should the project team do?

  • A. Demo the incomplete feature at the sprint retrospective.
  • B. Deploy the functionality that was presented to the users.
  • C. Continue with sprints until the product backlog is empty.
  • D. Wait to complete all user stories that are in development.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: B
In Agile/Scrum, only completed and accepted work (meeting the Definition of Done) should be deployed or released. Since the team demonstrated functionality in the sprint review that impressed users and is ready for production, that portion can be safely deployed. The incomplete feature that wasn’t demoed is not ready, so it should not be deployed. Agile promotes incremental delivery—you don’t need to wait for all features to be completed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...