During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three.)
Why not the others?
❌ B. End user – While their input is valuable for requirements and usability, they are not typically required in risk assessment unless their use patterns introduce risk.
❌ E. Product owner – Common in Agile projects, but not a required attendee in all project environments. If used, their presence may be helpful but not mandatory for the risk assessment in a general project management context.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month, 1 week ago