exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 406 discussion

Actual exam question from PMI's CAPM
Question #: 406
Topic #: 1
[All CAPM Questions]

An adaptive team's velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project.

How should the project manager calculate the anticipated velocity for future sprints?

  • A. Add a 30% buffer to the velocity to calculate future velocity.
  • B. Change the adaptive tool that the team is using to calculate velocity.
  • C. Use the velocity of the last sprint, as it is the most recent one to share.
  • D. Calculate the average of the past five sprints to predict future velocity.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: D
When estimating future velocity in an adaptive (Agile) project, it is best to: Smooth out anomalies (like a sprint with reduced capacity due to vacations). Use the average velocity over a reasonable number of recent sprints (typically 3–5) to get a more reliable prediction. This approach accounts for variations and provides a realistic forecast for how much work the team can deliver per sprint going forward.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...