exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 408 discussion

Actual exam question from PMI's CAPM
Question #: 408
Topic #: 1
[All CAPM Questions]

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization.

Which document should be used in this case?

  • A. Business case
  • B. Project charter
  • C. Project plan
  • D. Budget requirement
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: B
The project charter is the document that: Formally authorizes the existence of a project. Grants the project manager the authority to apply organizational resources to project activities. Serves as a reference for understanding project objectives, key stakeholders, high-level requirements, and the project sponsor’s commitment. In this case, the project manager needs formal authority to proceed—the project charter provides this.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...