A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear.
What should the project manager do next?
A.
Add the issue to the project issue log, as it will impact the project performance.
B.
Add the risk to the project risk register, as the lack of solutions could impact how the product is built.
C.
Facilitate a brainstorming session for the team to discuss ideas to solve the problem.
D.
Meet with the project sponsor to understand their vision on how to address the problem.
Why the other options are less appropriate:
A. Add the issue to the project issue log: This is reactive and passive. While logging the issue is important, it doesn’t help resolve the uncertainty or move the team forward.
B. Add the risk to the risk register: This is a valid action, but not the next best step. Identifying it as a risk is important, but alone won’t help the team generate solutions.
D. Meet with the project sponsor: This could be useful later, but the problem is lack of clear solutions—not necessarily lack of sponsor direction.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month ago