A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear.

What should the project manager do next?

  • A. Add the issue to the project issue log, as it will impact the project performance.
  • B. Add the risk to the project risk register, as the lack of solutions could impact how the product is built.
  • C. Facilitate a brainstorming session for the team to discuss ideas to solve the problem.
  • D. Meet with the project sponsor to understand their vision on how to address the problem.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: C
Why the other options are less appropriate: A. Add the issue to the project issue log: This is reactive and passive. While logging the issue is important, it doesn’t help resolve the uncertainty or move the team forward. B. Add the risk to the risk register: This is a valid action, but not the next best step. Identifying it as a risk is important, but alone won’t help the team generate solutions. D. Meet with the project sponsor: This could be useful later, but the problem is lack of clear solutions—not necessarily lack of sponsor direction.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...