A project manager is working on a project that is in the planning stage. In order to show the project's progress to the sponsor, the project manager will track significant events in the project life cycle. These events indicate that certain achievements are being met in the project.

Which event is being planned?

  • A. Milestones
  • B. Duration
  • C. Kickoff
  • D. Schedule
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: A
In project management, milestones are significant events or points in the project timeline that indicate the completion of major deliverables or phases. They are used to track progress and demonstrate that certain achievements or goals have been reached — which is exactly what the project manager in this scenario wants to show the sponsor. Why the other options are incorrect: B. Duration Refers to the length of time a task takes — not a specific event or achievement. C. Kickoff The kickoff meeting is a one-time event at the start of project execution, not a method of tracking progress through multiple events. D. Schedule The schedule outlines the sequence and timing of tasks, but it includes many details and doesn't specifically refer to key progress checkpoints.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...