In an agile project, when should story prioritization be performed?

  • A. Within the first half of the project.
  • B. Anytime during the project if the project manager allows it.
  • C. Within the first half of the project, except for high-priority stories.
  • D. Anytime during the project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: D
In Agile projects, story prioritization is an ongoing activity. It happens throughout the project, not just at the beginning or during a specific phase. The Product Owner is responsible for maintaining and prioritizing the product backlog. Backlog refinement (also called grooming) happens continuously, and prioritization can occur before each sprint or anytime new information arises. Agile encourages responding to change, so prioritization is flexible and revisited often based on stakeholder feedback, changing needs, or new risks/opportunities.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...