Question #: 453
Topic #: 1
[All CAPM Questions]

A program consists of four agile teams. Each team has a separate daily standup. Later each day, there is another standup meeting attended by one member from each team.

Which Scrum technique is this?

  • A. Disciplined Agile® (DA™)
  • B. Large Scale Scrum (LeSS)
  • C. Scaled Agile Framework (SAFe®)
  • D. Scrum of Scrums
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: D
When multiple agile teams coordinate via a daily representative meeting after individual team standups, this is called a Scrum of Scrums.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...