What is the next step for a business analyst after the stakeholders have validated the requirements?

  • A. Update the project management plan.
  • B. Update the requirements traceability matrix.
  • C. Update the requirements.
  • D. Update the work breakdown structure (WBS).
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: B
After the stakeholders have validated the requirements, the next step for the business analyst is to: Ensure that each approved requirement is properly traced through the project lifecycle — from origin to implementation and testing. This is done using the Requirements Traceability Matrix (RTM), which: Links each requirement to business needs, project objectives, deliverables, and test cases. Helps ensure that all requirements are fulfilled and that nothing is overlooked. Facilitates impact analysis if changes are proposed later.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...