In which project performance domain is the work breakdown structure (WBS) developed?

  • A. Delivery performance
  • B. Project work
  • C. Development approach and life cycle
  • D. Planning
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: D
Why the other options are incorrect: A. Delivery performance Focuses on how well the project outputs are delivered, not the creation of planning documents like the WBS. B. Project work Refers to executing the work, not planning how to break it down. C. Development approach and life cycle Defines the methodology and phases, but the WBS is part of detailed planning within the chosen approach.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...