Actual exam question from PMI's CAPM
Question #: 468
Topic #: 1
[All CAPM Questions]

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client's project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

  • A. Business management plan
  • B. Resource management plan
  • C. Cost management plan
  • D. Stakeholder engagement plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: B
Why the other options are incorrect: A. Business management plan This is not a standard PMBOK plan and doesn’t apply in this context. C. Cost management plan This defines how costs are estimated, budgeted, and controlled, but it does not assign responsibility for securing resource budgets. D. Stakeholder engagement plan Focuses on communication and involvement strategies for stakeholders — not resource acquisition or budget responsibilities.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...