Why the other options are incorrect:
❌ B. Monitor Risk Costs
This is not a standard risk management process. While cost is part of risk impact, there is no formal process called “Monitor Risk Costs.”
❌ E. Estimate Risk Activity Resources
This sounds like a mix of resource estimation and risk analysis, but it is not part of the standard risk management processes. Resource estimation is part of resource management, not risk.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month ago