Which three processes are generally included in risk management? (Choose three.)

  • A. Identify Risks
  • B. Monitor Risk Costs
  • C. Perform Qualitative Risk Analysis
  • D. Plan Risk Responses
  • E. Estimate Risk Activity Resources
Show Suggested Answer Hide Answer
Suggested Answer: ACD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: ACD
Why the other options are incorrect: ❌ B. Monitor Risk Costs This is not a standard risk management process. While cost is part of risk impact, there is no formal process called “Monitor Risk Costs.” ❌ E. Estimate Risk Activity Resources This sounds like a mix of resource estimation and risk analysis, but it is not part of the standard risk management processes. Resource estimation is part of resource management, not risk.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...