exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 477 discussion

Actual exam question from PMI's CAPM
Question #: 477
Topic #: 1
[All CAPM Questions]

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

  • A. Risk burnup and control chart
  • B. Customer satisfaction index and workload
  • C. Average burndown and velocity
  • D. Average velocity and cycle time
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: D
✅ Average Velocity Measures the amount of work completed in a fixed iteration (e.g., story points per sprint). Helps predict how many sprints remain to finish the remaining backlog. ✅ Cycle Time Measures the time it takes for a single item (e.g., a user story) to go from start to finish. Useful in Kanban or flow-based systems to forecast delivery timelines. Combining these gives you a predictive model: How much work remains? How fast is the team completing work? → Therefore, how much time is likely remaining?
upvoted 1 times
...
JesseChou_123
1 month, 1 week ago
Selected Answer: D
Why the other options are less suitable: A. Risk burnup and control chart Useful for tracking risk and process stability but not directly for predicting project duration. B. Customer satisfaction index and workload Important for quality and resource planning but not predictive of project completion time. C. Average burndown and velocity Burndown charts show remaining work but average burndown is not a standard metric; velocity alone is insufficient without cycle time.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...