Why other options are less complete or less accurate:
B. Project manager, business analyst, and key stakeholders
The project manager typically oversees project execution rather than directly defining requirements.
C. Business analyst, product team, and key stakeholders
The product team may not be involved in early requirement identification, especially outside of product development contexts.
D. Project manager, business analyst, and project sponsor
Missing key stakeholders is a gap since they provide critical input for requirements.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
3 weeks, 1 day agoJesseChou_123
3 weeks, 6 days ago