Question #: 498
Topic #: 1
[All CAPM Questions]

A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?

  • A. Plan Communications Management
  • B. Perform Qualitative Risk Analysis
  • C. Plan Stakeholder Engagement
  • D. Perform Integrated Change Control
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: D
Key here is "switch" thus "change"
upvoted 1 times
...
JesseChou_123
1 month, 1 week ago
Selected Answer: D
When a project sponsor changes during the planning phase, this is a significant change that may affect project scope, objectives, or plans. The Integrated Change Control process is used to review, evaluate, approve or reject changes to the project plans.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...