In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from reoccurring?

  • A. Extend the delivery time for the product since the management reserve allows it.
  • B. Identify possible reasons for the delay and consult the risk register for corrective actions.
  • C. Observe the project team's performance for the next two iterations before taking any action.
  • D. Temporarily use another team for the next iteration and evaluate their performance.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: B
When a team consistently fails to deliver on time, the first step is to investigate the root causes of the delay. Reviewing the risk register helps determine if the delays are known risks and if there are predefined corrective actions. This approach is proactive and data-driven, helping prevent future delays through informed adjustments.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...