The project manager needs to obtain proposals on costs of supplies purchased from an external source. In order to conduct this in a fair and unbiased way, what should the project manager conduct?
A bidder conference (also called a vendor or pre-bid conference) is held to communicate requirements and expectations clearly to all potential suppliers.
It ensures a fair, transparent, and unbiased process for obtaining proposals or bids.