Exam CAPM topic 1 question 501 discussion

Actual exam question from PMI's CAPM
Question #: 501
Topic #: 1
[All CAPM Questions]

The project manager needs to obtain proposals on costs of supplies purchased from an external source. In order to conduct this in a fair and unbiased way, what should the project manager conduct?

  • A. Procurement conference
  • B. Stakeholder meeting
  • C. Stakeholder conference
  • D. Bidder conference
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: D
A bidder conference (also called a vendor or pre-bid conference) is held to communicate requirements and expectations clearly to all potential suppliers. It ensures a fair, transparent, and unbiased process for obtaining proposals or bids.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...