exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 512 discussion

Actual exam question from PMI's CAPM
Question #: 512
Topic #: 1
[All CAPM Questions]

During execution of a project, a team could not reach consensus on the decision-making approach. Which document should the team member refer to?

  • A. Project team charter
  • B. Project management plan
  • C. Project team assignments
  • D. Project issue log
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: A
The Project team charter defines how the team will make decisions, resolve conflicts, set expectations, and communicate. It outlines the team operating guidelines, including decision-making approaches (e.g., consensus, majority vote, autocratic), ground rules, values, and norms.
upvoted 1 times
...
JesseChou_123
1 month, 1 week ago
Selected Answer: A
Why the other options are less suitable: B. Project management plan Outlines how the project will be executed and controlled but does not typically define team-specific decision-making processes. C. Project team assignments Lists roles and assignments, not decision-making rules. D. Project issue log Tracks issues but does not guide decision-making processes.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...