exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 376 discussion

Actual exam question from PMI's CAPM
Question #: 376
Topic #: 1
[All CAPM Questions]



Lucia (product owner) confirms the final deliverables have just been approved and that they are right on schedule. Lucia will meet with the client and tell him the good news. After the news is presented to the client, the client requests for an additional feature to be added.

What documentation should Lucia have obtained since the final deliverables were approved?

  • A. Lessons learned
  • B. Project management plan
  • C. Sign-off
  • D. Scope definition
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: C
Keyword "approved" which = sign-off
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.