The project manager has the following information about the estimated duration for an activity:
✑ Most likely [tM] `" 15 days
✑ Pessimistic [tP] `" 20 days
✑ Optimistic [tO] `" 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?