exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 1 question 101 discussion

Actual exam question from PMI's PMI-SP
Question #: 101
Topic #: 1
[All PMI-SP Questions]

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?

  • A. One
  • B. Five
  • C. Four
  • D. Zero
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
The path of ABDHJ will take 21 days to complete and cannot exceed 27 days or else the project will be late. If Activity B takes four additional days and Activity D takes two additional days, this adds (4+2= 6) six days to the path, bringing the path's duration to exactly (21+6 = 27) twenty seven days. There is no available float left for Activity E or H. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates.
Incorrect Answers:
A, B, C: There is no float available because the path's duration has increased to 27 days.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
aleemulislam
7 months, 1 week ago
ABEHJ path is also there, which will take 22 days to complete, plus 6 days will make this path critical
upvoted 1 times
...
Mopar
7 months, 3 weeks ago
This question is repeated.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago