Actual exam question from PMI's PMI-SP
Question #: 39
Topic #: 2
[All PMI-SP Questions]

You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team for each of their activities. What is the formula used for PERT?

  • A. O+M+P
  • B. (O+M+P)/3
  • C. (O+4M+P)/6
  • D. Average of the estimates
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
PERT uses the formula of (O+4M+P)/6 to predict the duration of the project activities and the overall project schedule. Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates: Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide more accuracy.
Incorrect Answers:
A: This is not a valid formula.
B: This is the formula for the three-point estimate. Note the PERT, while similar, uses 4M and divides the result by six factors.
D: This almost describes the three-point estimate, but does not answer the question about PERT.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mopar
7 months, 2 weeks ago
Repeated question
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago