You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?
Suggested Answer:A🗳️
Schedule data is not an input to the control schedule process. Organizational process assets are the final input to the control schedule process. The inputs of schedule control process are as follows: Project Management Plan Project Schedule Work Performance Integration Organizational Process Assets Incorrect Answers: B: Work performance information is an input to the control schedule process. C: The project management plan is an input to the control schedule process. D: The project schedule is an input to the control schedule process.
This section is not available anymore. Please use the main Exam Page.PMI-SP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Mopar
7 months, 2 weeks ago