Exam PMI-SP topic 2 question 136 discussion

Actual exam question from PMI's PMI-SP
Question #: 136
Topic #: 2
[All PMI-SP Questions]

You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

  • A. Schedule data
  • B. Work performance information
  • C. Project management plan
  • D. Project schedule
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Schedule data is not an input to the control schedule process. Organizational process assets are the final input to the control schedule process. The inputs of schedule control process are as follows: Project Management Plan Project Schedule Work Performance Integration Organizational Process Assets
Incorrect Answers:
B: Work performance information is an input to the control schedule process.
C: The project management plan is an input to the control schedule process.
D: The project schedule is an input to the control schedule process.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mopar
7 months, 2 weeks ago
Work performance information is an output.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago