exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 71 discussion

Actual exam question from PMI's PMI-ACP
Question #: 71
Topic #: 1
[All PMI-ACP Questions]

While reviewing the sprint burn down during a stand up, the scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.
What should the scrum team do?

  • A. For upcoming sprints, have QA team members ensure that their respective skill sets are considered when accepting stories
  • B. Have QA team members with the appropriate skill sets spend extra to help the team succeed
  • C. Ensure that QA team members who lack the appropriate skill up for training within the next few weeks
  • D. Ask QA team members experienced with the new automation framework to cross-train the other QA members
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
diligentstudent
Highly Voted 3 years, 1 month ago
Ask for spending "extra time" doesn't feel like the right solution. Cross-training can provide a definitive solution to the issue.
upvoted 12 times
...
Petrevski
Most Recent 6 months, 3 weeks ago
Selected Answer: D
D = correct
upvoted 2 times
...
Minhha3
6 months, 3 weeks ago
Vote D
upvoted 2 times
...
Smokeyofficiial
7 months, 2 weeks ago
Option D. The issue here is that some QA team members were unable to use the new automation framework, causing a bottleneck that slowed down the sprint progress. To address this issue, the scrum team should take steps to ensure that all QA team members have the necessary skills to use the automation framework. One way to do this is to ask experienced QA team members who are already familiar with the automation framework to cross-train other team members. This will help ensure that everyone has the skills needed to complete the work efficiently, which should help the team catch up on their sprint burn down.
upvoted 3 times
...
InvisibleBeing
9 months, 1 week ago
Selected Answer: D
D is correct. The fastest way to train someone on your team is to have an experience developer work with or train the new developer. The team is already behind schedule and if you do not have a good training plan, the project will suffer even more.
upvoted 1 times
...
gogiap
1 year ago
I Vote D
upvoted 1 times
...
cozyhead
1 year, 2 months ago
Selected Answer: D
D for me
upvoted 1 times
...
richck102
1 year, 3 months ago
i vote D
upvoted 2 times
...
JackNguyenvn
1 year, 7 months ago
I choose D
upvoted 3 times
...
Oshera
1 year, 10 months ago
For this I think B maybe correct. Given that the scenario has them already within a project, having deliverables etc. they may not have the time to cross train. The best fix for that would be to have the ones with the knowledge to assist. Also it says extra time not work over time. Extra time could be within working hours.
upvoted 1 times
...
snow5
2 years, 11 months ago
D is the right answer
upvoted 4 times
...
GPena
2 years, 12 months ago
I think it is D
upvoted 3 times
...
tsangckl
3 years ago
My pick is D
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago