Exam CAPM topic 1 question 84 discussion

Actual exam question from PMI's CAPM
Question #: 84
Topic #: 1
[All CAPM Questions]

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

  • A. Monitor project stakeholder relationships using engaging strategies and plans
  • B. Send all project documents to stakeholders each time they are modified
  • C. Schedule monthly meetings with the stakeholders, including team members
  • D. Engage only with the project sponsors
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Rocket20
1 year ago
Selected Answer: A
The answer is A
upvoted 1 times
...
ChymKuBoy
1 year, 2 months ago
Selected Answer: A
A for sure
upvoted 1 times
...
romelodoctr
1 year, 2 months ago
Selected Answer: A
A is the answer
upvoted 1 times
...
Zmfoutch
1 year, 5 months ago
Selected Answer: A
High degree of change indicates agile/ adaptive project management, which encourages frequent communication with stakeholders.
upvoted 1 times
...
anfacer
1 year, 7 months ago
Selected Answer: A
C- Is not correct as the agile encourage frequent meetings with stakeholders, even daily based. There is no monthly recomendation. A- is more correct for me as claudiapatricia says
upvoted 2 times
...
claudiapatricia777
1 year, 8 months ago
Selected Answer: A
Projects experiencing a high degree of change require active engagement and participation with project stakeholders. To facilitate timely, productive discussion and decision making, adaptive teams engage with stakeholders directly rather than going through layers of management. Often the client, user, and developer exchange information in a dynamic co-creative process that leads to more stakeholder involvement and higher satisfaction. Regular interactions with the stakeholder community throughout the project mitigate risk, build trust, and support adjustments earlier in the project cycle, thus reducing costs and increasing the likelihood of success for the project. In order to accelerate the sharing of information within and across the organization, agile methods promote aggressive transparency. The intent of inviting any stakeholders to project meetings and reviews or posting project artifacts in public spaces is to surface as quickly as possible any misalignment, dependency, or other issue related to the changing project
upvoted 4 times
...
MoonManBlue
3 years, 10 months ago
A makes sense, although I don't see it in the 6th edition
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...