The project manager implemented the stakeholder engagement plan and realized that some updates should be made. Which components of the project management plan should be modified?
A.
Project charter and stakeholder engagement plan
B.
Risk management plan and stakeholder engagement plan
C.
Communications management plan and stakeholder engagement plan
D.
Project charter and communications management plan
Why the other options are incorrect:
A. Project charter – This is not updated for engagement or communication changes.
B. Risk management plan – Not directly relevant unless the changes to stakeholder engagement introduce new risks.
D. Project charter and communications management plan – The project charter is not updated once the project is approved.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123