Which are the competing constraints that a project manager should address when tailoring a project?

  • A. Cost, scope, schedule
  • B. Sponsorship, risk, quality
  • C. Schedule, sponsorship, scope
  • D. Resources, quality, communication
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Rocket20
11 months, 2 weeks ago
Selected Answer: A
A. Competing constraints of scope, schedule, cost, resources, quality and risk should all be addressed by tailoring
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...