Analogous estimating is a technique for estimating the duration or cost of an activity or a project using historical
data from a similar activity or project
page 200 PMBOK
Analogous is based on past knowlege. A) is not fully correct- a specializaded knowledge does not imply cost knowlege (unless you are expert in a purchasing area)
upvoted 2 times
...