Question #: 122
Topic #: 1
[All CAPM Questions]

In an agile and adaptive project, which scope management entity involves stakeholder engagement?

  • A. Collect Requirements
  • B. Create work breakdown structure (WBS)
  • C. Plan Scope Management
  • D. Scope Baseline
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
10 months, 3 weeks ago
Selected Answer: A
Pg. 133, PMBOK 6th Edition. You collect requirements as you go, which constitute the backlog. Agile tries to take less time agreeing on scope and establishes and defines it as the project moves along; product owner and stakeholders help with requirements as project goes. Answer. A. Collect Requirements
upvoted 3 times
...
wootteo
10 months, 4 weeks ago
A Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet objectives.
upvoted 2 times
...
Jerin33063
1 year, 5 months ago
Page 138
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.