Actual exam question from PMI's CAPM
Question #: 64
Topic #: 1
[All CAPM Questions]

Which of the following are outputs from the process of creating a work breakdown structure (WBS)?

  • A. Project scope statement and accepted deliverables
  • B. Scope baseline and project documents update
  • C. Accepted deliverables and enterprise environmental factors
  • D. Scope baseline and work performance information
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Rocket20
10 months ago
Selected Answer: B
See 5.4.3 Create WBS: Outputs
upvoted 1 times
...
Cat2023
12 months ago
B - pg 570 6th ed 1. Scope Baseline 2. Project Documents Updates
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago