Why the other options are incorrect:
A. Compiling a list of known risks and preparing responses to them
❌ This aligns more with Plan Risk Responses and earlier risk identification steps.
B. Assessing the probability of occurrence and impact for every risk in the risk register
❌ This describes Perform Qualitative Risk Analysis, which is about ranking and prioritizing risks — not numerical modeling.
C. Evaluating the contingency and management reserves required for the project
❌ This is part of Reserve Analysis, which may be informed by quantitative risk data, but it is not the main goal of this process.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
4 days, 19 hours agoMoonManBlue
8 months, 3 weeks ago