The project manager is creating the communications management plan. Which group of inputs is required to begin?

  • A. Work performance reports, change requests, and risk register
  • B. Work performance data, project documents, and stakeholder engagement plan
  • C. Project charter, project management plan, and project documents
  • D. Work performance data, stakeholder register, and team management plan
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
Highly Voted 3 years, 9 months ago
C-Project Charter, Project Management Plan, Project Documents 10.1
upvoted 7 times
...
lily_dice
Most Recent 1 month, 1 week ago
Selected Answer: C
C the project objectives should come first
upvoted 1 times
...
DelMario1
1 month, 1 week ago
Selected Answer: C
C is the best answer
upvoted 1 times
...
Assad1981
9 months ago
Option C
upvoted 2 times
...
Ajilox5
11 months, 1 week ago
C is the right answer
upvoted 1 times
...
ghjuh1
12 months ago
10.1 Plan Communications Management .1 Inputs .1 Project charter .2 Project management plan .3 Project documents .4 Enterprise environmental factors .5 Organizational process assets
upvoted 1 times
...
ChymKuBoy
1 year, 1 month ago
Selected Answer: C
C for sure
upvoted 1 times
...
jenza
1 year, 2 months ago
Selected Answer: C
C - charter, pm plan, and docs
upvoted 1 times
...
AyandaCAPM
1 year, 2 months ago
Selected Answer: C
To create the Plan Communications Management, necessary inputs are needed such as the project management plan, organizational process assets, and enterprise environmental factors. The project manager also needs to get the stakeholder register to know who the stakeholders are.
upvoted 1 times
...
bob523523
1 year, 3 months ago
C. Project charter, project management plan, and project documents
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...