To create the Plan Communications Management, necessary inputs are needed such as the project management plan, organizational process assets, and enterprise environmental factors. The project manager also needs to get the stakeholder register to know who the stakeholders are.
C. Project charter, project management plan, and project documents
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MoonManBlue
Highly Voted 3 years, 7 months agoAssad1981
Most Recent 7 months agoAjilox5
9 months, 2 weeks agoghjuh1
10 months, 1 week agoChymKuBoy
11 months, 2 weeks agojenza
1 year agoAyandaCAPM
1 year agobob523523
1 year, 1 month ago