according to the PMBOK guide it should be Develope a schedule:When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in the Develop Schedule process.
B. Define Activities
When developing the project schedule, the process that involves decomposition and rolling wave planning techniques is "Define Activities." In this process, the project manager breaks down the project work into smaller, more manageable components or activities. Decomposition is the technique of subdividing project deliverables and project work into smaller, more manageable parts.
Processes that are performed continuously throughout the project. The process Define Activities may
occur throughout the project life cycle, especially if the project uses rolling wave planning or an adaptive
development approach. Many of the monitoring and control processes are ongoing from the start of the
project, until it is closed out.
Decomposition and Rolling wave planning is a T&T of Define activities pg 174
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Sumbo
Highly Voted 1 year, 9 months agobramirezb593
1 year, 4 months agoUlrichIng
Highly Voted 4 years agoshubu2276
Most Recent 9 months, 2 weeks agoAssad1981
1 year, 1 month agogarlicbread
1 year, 3 months agoeminema07
1 year, 5 months agoNavz
1 year, 9 months ago