When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process:

  • A. Develop Schedule
  • B. Define Activities
  • C. Define Scope
  • D. Collect Requirements
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sumbo
Highly Voted 1 year, 9 months ago
according to the PMBOK guide it should be Develope a schedule:When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in the Develop Schedule process.
upvoted 5 times
bramirezb593
1 year, 4 months ago
That's so untrue
upvoted 4 times
...
...
UlrichIng
Highly Voted 4 years ago
B. Define Activities
upvoted 5 times
...
shubu2276
Most Recent 9 months, 2 weeks ago
Selected Answer: B
B. Define Activities When developing the project schedule, the process that involves decomposition and rolling wave planning techniques is "Define Activities." In this process, the project manager breaks down the project work into smaller, more manageable components or activities. Decomposition is the technique of subdividing project deliverables and project work into smaller, more manageable parts.
upvoted 2 times
...
Assad1981
1 year, 1 month ago
B is correct answer
upvoted 1 times
...
garlicbread
1 year, 3 months ago
Rolling Wave Planning is one of the techniques in the ‘Define Activities’ process under Project Time Management.
upvoted 2 times
...
eminema07
1 year, 5 months ago
Selected Answer: B
pg 185
upvoted 2 times
...
Navz
1 year, 9 months ago
Processes that are performed continuously throughout the project. The process Define Activities may occur throughout the project life cycle, especially if the project uses rolling wave planning or an adaptive development approach. Many of the monitoring and control processes are ongoing from the start of the project, until it is closed out. Decomposition and Rolling wave planning is a T&T of Define activities pg 174
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago