Which two processes should be used to influence costs in the early stages of a project?

  • A. Estimate Costs and Determine Budget
  • B. Plan Cost Management and Estimate Activity Durations
  • C. Control Quality and Control Costs
  • D. Plan Stakeholder Engagement and Plan Communications Management
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
041ba31
11 months, 2 weeks ago
Selected Answer: A
A. Estimate Costs and Determine Budget To influence costs in the early stages of a project, the two processes that should be used are: 1. Estimate Costs: This process involves developing an approximation of the monetary resources required to complete project activities. It is performed early in the project to provide an initial understanding of the project's cost implications. 2. Determine Budget: This process takes the cost estimates from the Estimate Costs process and allocates them to specific project activities or work packages. It establishes the approved budget for the project and helps in managing costs throughout the project's lifecycle. By using these two processes, project managers can set cost expectations, allocate resources effectively, and establish a budget framework to guide cost management from the project's inception.
upvoted 2 times
...
Caspian
1 year, 4 months ago
Selected Answer: A
I think its A. I used Chatgpt to double check and its A
upvoted 2 times
...
garlicbread
1 year, 4 months ago
Selected Answer: A
I think activity duration doesn't influence the cost
upvoted 2 times
...
PM01950
1 year, 5 months ago
Selected Answer: B
Right is B
upvoted 1 times
...
adingmaki
1 year, 6 months ago
Selected Answer: B
INFLUENCE. more activities = more cost
upvoted 1 times
...
pbbade
1 year, 7 months ago
The right answer is B
upvoted 1 times
...
Navz
1 year, 10 months ago
7.1 Plan Cost Management—The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.
upvoted 1 times
...
wencai002
3 years, 3 months ago
influence is not the same as estimate
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...