A project stakeholder is requesting changes to the project plan. Which process group addresses this?

  • A. Initiating Process Group
  • B. Planning Process Group
  • C. Executing Process Group
  • D. Monitoring and Controlling Process Group
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
pahkhu
10 months, 1 week ago
We can say that. Change requests are outputs of monitor and control process group. please comment
upvoted 2 times
...
bigntall1
1 year ago
Selected Answer: D
M&C PROCESS GROUP
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.