The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?
A.
Team values, team agreements, and conflict resolution process
B.
Conflict resolution process, communication guidelines, and meeting schedules
C.
Team roles and responsibilities, team management, and training plan
D.
Resource requirements, resource assignments, and team performance assessments
Team performance assessments can’t happen until the team is developed ( 9.4) this is 9.1, even with regard to an iterative approach, plan resource management is the HOW we will estimate activity resources (9.2), acquire resources (9.3), develop team (9.4), manage team ( 9.5) and control resources (9.6).
C is the correct answer.
In pg 318 appears the plan may include: Identification of resources, aquiring resources, roles and responsabilities, project charts, resource management, training, team development, resource control, recognition plan
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
pahkhu
10 months agoImMaGiiCz
11 months, 1 week agoChymKuBoy
11 months, 2 weeks agoZmfoutch
1 year, 3 months agoZmfoutch
1 year, 3 months agoNavz
1 year, 3 months agoanfacer
1 year, 4 months agoanfacer
1 year, 4 months ago