Exam CAPM topic 1 question 91 discussion

Actual exam question from PMI's CAPM
Question #: 91
Topic #: 1
[All CAPM Questions]

The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?

  • A. Team values, team agreements, and conflict resolution process
  • B. Conflict resolution process, communication guidelines, and meeting schedules
  • C. Team roles and responsibilities, team management, and training plan
  • D. Resource requirements, resource assignments, and team performance assessments
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
pahkhu
10 months ago
Resource requirements is an output of Estimate Activity resources process and Project team assignments is an output of Acquire resources process
upvoted 2 times
...
ImMaGiiCz
11 months, 1 week ago
Selected Answer: C
C for sure
upvoted 2 times
...
ChymKuBoy
11 months, 2 weeks ago
Selected Answer: C
C for sure
upvoted 1 times
...
Zmfoutch
1 year, 3 months ago
Selected Answer: C
Team assessments happen in develop team, as an output. Therefore they are not an input to a previous process in the planning process.
upvoted 2 times
...
Zmfoutch
1 year, 3 months ago
Team performance assessments can’t happen until the team is developed ( 9.4) this is 9.1, even with regard to an iterative approach, plan resource management is the HOW we will estimate activity resources (9.2), acquire resources (9.3), develop team (9.4), manage team ( 9.5) and control resources (9.6). C is the correct answer.
upvoted 1 times
...
Navz
1 year, 3 months ago
C refer to page 318
upvoted 2 times
...
anfacer
1 year, 4 months ago
team performance assessments is in Develop Team Output, not Plan Output
upvoted 2 times
...
anfacer
1 year, 4 months ago
Selected Answer: C
In pg 318 appears the plan may include: Identification of resources, aquiring resources, roles and responsabilities, project charts, resource management, training, team development, resource control, recognition plan
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago