The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?
After a deliverable the project team verify compliance. If pass then is the customer who should accept it.
Deliberable->Verified Deliberable->Accepted Deliverable
Correct answer is C. Verified Deliverables and Validated Changes Two important outputs of the Control Quality process are Verified Deliverables and Validated changes. And after going through this article you will understand why we cover them together. As soon as a Deliverable of the project is ready, the project team inspects it to find any defects.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
HPouria
7 months, 1 week agopahkhu
10 months, 2 weeks agoChymKuBoy
1 year agoHungdv
1 year, 3 months agoDJMCAPM
1 year, 3 months agome22
1 year, 5 months agoanfacer
1 year, 5 months agomeg002
1 year, 5 months agoOlamipo
3 years, 2 months agoUlrichIng
3 years, 7 months ago