exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 134 discussion

Actual exam question from PMI's CAPM
Question #: 134
Topic #: 1
[All CAPM Questions]

During which process of Project Cost Management does a project manager produce the cost baseline?

  • A. Estimate Costs
  • B. Control Schedule
  • C. Determine Budget
  • D. Develop Project Charter
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 4 weeks ago
Selected Answer: C
Why the other options are incorrect: A. Estimate Costs: This is where individual cost estimates for activities or resources are developed, but not aggregated into a budget. B. Control Schedule: This is part of Project Schedule Management, not directly related to cost or budgets. D. Develop Project Charter: This is an initiating process that defines high-level funding requirements but does not produce the detailed cost baseline.
upvoted 1 times
...
alex903
1 year ago
C. Pg. 231; sixth edition book.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...