Actual exam question from PMI's CAPM
Question #: 66
Topic #: 1
[All CAPM Questions]

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

  • A. Defining, sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are viewed as a single process.
  • B. The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
  • C. An iterative scheduling and on-demand, pull-based scheduling will be required.
  • D. To address the full delivery schedule, a range of techniques may be needed and then need to be adapted.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
wencai002
Highly Voted 3 years, 9 months ago
C P92 in the table generally manifest as iterative scheduling and on-demand, pull-based scheduling, as discussed in the Key Trends
upvoted 5 times
...
[Removed]
Highly Voted 1 year, 11 months ago
I think again this is a tricky question because while most of you think C., where that answer I think is wrong is because in the PMBOK page 178, it does say it "generally manifests" as iterative scheduling and on-demand, pull-based scheduling. BUT the answer actually says in C. REQUIRED. It's NOT required. It's generally that. This is why C. is wrong, but 90% of you would pick C. and get it wrong. The entire point of adaptive is that it's flexible and not always following anything to a T. Keep that in mind in general with anything agile/flexible/adaptive/iterative. It's very unique to the situation and nothing is ever in stone.
upvoted 5 times
...
Erry12
Most Recent 11 months, 1 week ago
Selected Answer: C
Pag 92 of Agile Practice
upvoted 1 times
Erry12
11 months, 1 week ago
Although it says manifest, not required. So B could be also right
upvoted 2 times
...
...
Pradnyasachin
1 year, 5 months ago
Selected Answer: C
In adaptive or Agile environments, scheduling often operates in an iterative manner, allowing for adjustments and refinements as the project progresses. Pull-based scheduling involves task prioritization based on immediate needs and demand, allowing the team to adapt their schedule based on evolving requirements and changes in priorities. This flexibility is integral to adapting and responding effectively to changes in an adaptive project environment.
upvoted 1 times
...
DHKaze
1 year, 6 months ago
pg.175 Under key concepts for project schedule management. When possible, the detailed project schedule should remain flexible throughout the project to adjust for knowledge gained, increased understanding of the risk, and value-added activities." nowhere in the PMBOK guide does it say that a pull-based scheduling is "REQUIRED".
upvoted 1 times
...
garlicbread
1 year, 10 months ago
Selected Answer: B
C is wrong because a pull base isn't required. Making that an incorrect answer. B is the next best option
upvoted 2 times
...
Rocket20
1 year, 10 months ago
Selected Answer: C
Key word "Iterative" for an adaptive environment. Please see Considerations for agile/ adaptive environments - first paragraph PMBOK 6th ed ebook pg 215
upvoted 1 times
...
Tadpole1
1 year, 11 months ago
Selected Answer: C
When working on the scheduling for an adaptive environment, the project manager should consider the following condition: C. An iterative scheduling and on-demand, pull-based scheduling will be required. In an adaptive environment, where requirements and project conditions are likely to change, traditional linear scheduling approaches may not be effective. Instead, an iterative scheduling approach is needed, where work is planned and scheduled in shorter iterations or increments. This allows for flexibility and the ability to adapt to changing requirements and priorities as new knowledge is gained throughout the project. On-demand, pull-based scheduling is also important in an adaptive environment. Rather than pre-determining the entire schedule upfront, work is scheduled based on the actual need and demand. As the project progresses, work is pulled into the schedule based on the availability of resources, the evolving priorities, and the feedback received.
upvoted 1 times
...
CalvinthePM
2 years, 2 months ago
Ch. 6 Project Schedule Management Pg. 178. Answer is C.
upvoted 1 times
...
limoncello
2 years, 4 months ago
Selected Answer: C
Adaptive environment uses iterative scheduling and on-demand, pull-based scheduling
upvoted 1 times
...
MP_2022
2 years, 5 months ago
The question didn't ask about key trends. It asked what to keep in mind when scheduling, which is why B is correct.
upvoted 3 times
...
claudiapatricia777
2 years, 6 months ago
Selected Answer: C
Adaptive approaches use short cycles to undertake work, review the results, and adapt as necessary. These cycles provide rapid feedback on the approaches and suitability of deliverables, and generally manifest as iterative scheduling and on-demand, pull-based scheduling, as discussed in the section on Key Trends and Emerging Practices in Project Schedule Management
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...