Exam CAPM topic 1 question 58 discussion

Actual exam question from PMI's CAPM
Question #: 58
Topic #: 1
[All CAPM Questions]

Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

  • A. Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.
  • B. Make surveys among the stakeholders and meet with the team once a month.
  • C. Create a social network and post news there.
  • D. Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
wineo38
9 months, 2 weeks ago
Selected Answer: A
Surveys take a while to get back, so A
upvoted 1 times
...
Rocket20
9 months, 3 weeks ago
Selected Answer: A
Please see Pg 402 e-book Considerations for agile/adaptive environments - posting artifacts in a transparent fashion, holding reg stakeholder reviews promote communication in addition to frequent checkpoints and access to information
upvoted 1 times
...
lauracecilia
9 months, 4 weeks ago
A. pg. 365 6th edition
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago