A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

  • A. Monitor and Control Project Work
  • B. Direct and Manage Project Work
  • C. Close Project or Phase
  • D. Perform Integrated Change Control
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
wineo38
9 months, 2 weeks ago
Selected Answer: D
That the process
upvoted 1 times
...
ale1231
2 years, 8 months ago
D. Perform Integrated Change Control
upvoted 2 times
...
UlrichIng
3 years, 6 months ago
D. Perform Integrated Change Control
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.