A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
The project manager's review of change requests for project documents, deliverables, and the project plan falls under the Perform Integrated Change Control process. This process ensures that all changes are managed systematically, considering their impact on the project's scope, schedule, cost, and other aspects.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month, 1 week agowineo38
11 months, 1 week agoale1231
2 years, 10 months agoUlrichIng
3 years, 8 months ago