Question #: 62
Topic #: 1
[All CAPM Questions]

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

  • A. Project charter, business documents, and project management plan
  • B. Agreements, scope baseline, and project management plan
  • C. Project charter, business case, and project management plan
  • D. Work performance data, enterprise environmental factors, and project management plan
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MFrankieG2022
Highly Voted 1 year, 5 months ago
key here is monitor in the question, so looking at performance is where it is at.
upvoted 7 times
...
TonyTucci
Highly Voted 11 months, 3 weeks ago
Key is Work Performance Data.
upvoted 5 times
...
JesseChou_123
Most Recent 1 month, 1 week ago
Selected Answer: D
During the "Monitor Stakeholder Engagement" process, a project manager would use a combination of Project Management Plan, Project Documents, Work Performance Data, and Enterprise Environmental Factors (EEF) and Organizational Process Assets (OPA).
upvoted 1 times
...
UlrichIng
3 years, 8 months ago
D. Work performance data, enterprise environmental factors, and project management plan
upvoted 4 times
...
MoonManBlue
3 years, 9 months ago
D is correct 13.4
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...