Which statement about identification and engagement of stakeholders during a project is correct?

  • A. Project stakeholders should be identified and engaged in every phase of the project to influence the success of the project directly.
  • B. Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.
  • C. Project stakeholders should be identified when the project charter is being completed and engaged during requirements gathering.
  • D. Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ushehwhehehe
9 months, 3 weeks ago
Selected Answer: A
Definitely
upvoted 1 times
...
ChymKuBoy
11 months, 2 weeks ago
Selected Answer: A
A for sure
upvoted 2 times
...
CalvinthePM
1 year, 1 month ago
From both Landini and PocketPrep, stakeholder identification is done in every process group. Answer is A.
upvoted 3 times
...
meg002
1 year, 5 months ago
correct answer is C. Identification of stakeholder is a continuous process throughout the project life cycle however project team is responsible to identify all possible key stakeholders at early stage of project and involve them in project planning phase, project may encounter a big failure if project team will not buy-in key stakeholders at early stages.
upvoted 1 times
anfacer
1 year, 4 months ago
The C answer says while charter is BEING developed, so the charter is still not done. When developing charter you only need to identify key stakeholders and Engagement is not done only during requirements but the whole project. So I would go to A as correct
upvoted 2 times
...
...
claudiapatricia777
1 year, 5 months ago
Selected Answer: A
A is correct
upvoted 3 times
...
MoonManBlue
3 years, 7 months ago
C is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago