exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 105 discussion

Actual exam question from PMI's PMI-ACP
Question #: 105
Topic #: 1
[All PMI-ACP Questions]

An agile team is planning the next iteration for a product release that has accumulated technical debt.
What should the team do?

  • A. Add code cleanup activities to the product backlog and request prioritization by the product owner
  • B. Add code cleanup activities to the next iteration and request clarification from the product owner
  • C. Add code cleanup activities to the next iteration and ask the product owner to end the current iteration
  • D. Add code cleanup activities to the next release backlog and request documentation from the product owner
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
diligentstudent
Highly Voted 3 years, 2 months ago
I believe "B" is incorrect. Why should a PO clarify technical tasks? Initially it's not a technical role who can perform that activity. "A" makes more sense to me.
upvoted 6 times
...
snow5
Highly Voted 3 years ago
It is clear from comments I have been thru so far that people who disagree with the answers do not read questions carefully, and thats why most people could not pass the exam. For example, in this question the question is asking about the team and what they should do, not about PO, for that's reason the answer is correct. but if the question was asking what PO should do then B is not considered correct. So read the questions carefully before put your answers.
upvoted 5 times
srv3
2 years, 11 months ago
I agree with B A. Add code cleanup activities to the product backlog and request prioritization by the product owner = there is no reason to add cleanup activities into the PB, it can be added directly into the SB. Next sprint is release sprint. B. Add code cleanup activities to the next iteration and request clarification from the product owner = Looks like correct answer. C. Add code cleanup activities to the next iteration and ask the product owner to end the current iteration = there is no reason to stop current sprint D. Add code cleanup activities to the next release backlog and request documentation from the product owner = there is no such artefact as "next release backlog"
upvoted 3 times
...
...
Petrevski
Most Recent 7 months ago
Selected Answer: A
А = correct B = wrong, what can clarify the PO regarding the technical debt? C/D = doesn't make sense.
upvoted 2 times
...
Minhha3
7 months, 2 weeks ago
Vote A
upvoted 1 times
...
InvisibleBeing
10 months ago
Selected Answer: A
A is correct. Any stories or work to deal with technical debt needs to be added in the Product Backlog and then needs be discussed with the PO to prioritize and include in the sprints.
upvoted 1 times
...
richck102
1 year, 4 months ago
i vote A
upvoted 1 times
...
JackNguyenvn
1 year, 7 months ago
A is correct
upvoted 2 times
...
thuha1704
1 year, 8 months ago
I choose A
upvoted 2 times
...
Admirable
2 years, 4 months ago
The tasks related to technical debt is apart of maintenance activities which should be included in the product backlog. The team will need to pay down on technical debt regularly and will need to include this in the refactoring and bug fixing efforts as part of iteration/sprint. The team therefore adds the tasks to the backlog so that it can be prioritized by the PO and to be addressed in future sprints.
upvoted 2 times
...
Admirable
2 years, 4 months ago
A is the best answer.
upvoted 1 times
...
yinhx2021
2 years, 5 months ago
Agree with diligentstudent's comment, why PO would clarify technical debts? I would go for answer A.
upvoted 2 times
...
tsangckl
3 years, 1 month ago
My answer is A
upvoted 1 times
...
praveenkumard23
3 years, 1 month ago
I agree with Answer A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel