I believe "B" is incorrect. Why should a PO clarify technical tasks? Initially it's not a technical role who can perform that activity. "A" makes more sense to me.
It is clear from comments I have been thru so far that people who disagree with the answers do not read questions carefully, and thats why most people could not pass the exam. For example, in this question the question is asking about the team and what they should do, not about PO, for that's reason the answer is correct. but if the question was asking what PO should do then B is not considered correct. So read the questions carefully before put your answers.
I agree with B
A. Add code cleanup activities to the product backlog and request prioritization by the product owner
= there is no reason to add cleanup activities into the PB, it can be added directly into the SB. Next sprint is release sprint.
B. Add code cleanup activities to the next iteration and request clarification from the product owner
= Looks like correct answer.
C. Add code cleanup activities to the next iteration and ask the product owner to end the current iteration
= there is no reason to stop current sprint
D. Add code cleanup activities to the next release backlog and request documentation from the product owner
= there is no such artefact as "next release backlog"
A is correct.
Any stories or work to deal with technical debt needs to be added in the Product Backlog and then needs be discussed with the PO to prioritize and include in the sprints.
The tasks related to technical debt is apart of maintenance activities which should be included in the product backlog. The team will need to pay down on technical debt regularly and will need to include this in the refactoring and bug fixing efforts as part of iteration/sprint. The team therefore adds the tasks to the backlog so that it can be prioritized by the PO and to be addressed in future sprints.
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
diligentstudent
Highly Voted 3 years, 2 months agosnow5
Highly Voted 3 years agosrv3
2 years, 11 months agoPetrevski
Most Recent 7 months agoMinhha3
7 months, 2 weeks agoInvisibleBeing
10 months agorichck102
1 year, 4 months agoJackNguyenvn
1 year, 7 months agothuha1704
1 year, 8 months agoAdmirable
2 years, 4 months agoAdmirable
2 years, 4 months agoyinhx2021
2 years, 5 months agotsangckl
3 years, 1 month agopraveenkumard23
3 years, 1 month ago