A protect manager needs to request outside support for a statement of work (SOW) that is not precise. Which kind of contract does the project manager need to create?
Time and material contracts (T&M). Time and material contracts (also called time and means) are a hybrid type of contractual arrangement with aspects of both cost-reimbursable and fixed-price contracts. They are often used for staff augmentation, acquisition of experts, and any outside support when a precise statement of work cannot be quickly prescribed.
A Time and Material contract type might be suitable when the scope of work or requirements are not well-defined. It allows for flexibility as it involves payments based on the time spent and the materials used. This contract type provides a degree of flexibility to accommodate changes and uncertainties in the project scope or SOW
Time & Material is used when SOW cannot be defined
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
UlrichIng
Highly Voted 3 years, 7 months agoMoonManBlue
Highly Voted 3 years, 7 months agoPradnyasachin
Most Recent 5 months, 1 week agoRocket20
10 months, 1 week agoTonyTucci
10 months, 2 weeks ago[Removed]
10 months, 2 weeks agoChymKuBoy
11 months, 3 weeks agoZmfoutch
1 year, 3 months agoDJMCAPM
1 year, 3 months agoDeepikaparas
1 year, 4 months ago