The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project
Procurement Management processes?

  • A. Work performance information
  • B. Bidder conferences
  • C. Complexity of procurement
  • D. Procurement management plan
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Pradnyasachin
6 months, 3 weeks ago
Selected Answer: C
The involvement of multiple vendors can significantly increase the complexity of procurement activities. Understanding and managing this complexity is crucial, encompassing aspects such as handling various contracts, ensuring coordination among vendors, managing different delivery schedules, and addressing potential conflicts or dependencies between vendors. The procurement management plan would also be crucial, but in this context, the complexity of managing multiple vendors is a significant consideration.
upvoted 1 times
...
Akneeka
1 year ago
Selected Answer: C
C-several vendors lend to complexity of the process
upvoted 1 times
...
ChymKuBoy
1 year, 1 month ago
Selected Answer: D
D for sure
upvoted 2 times
...
adingmaki
1 year, 1 month ago
basis of work = plan
upvoted 2 times
...
adingmaki
1 year, 1 month ago
Selected Answer: C
Agree with C. It's in the book. Tailoring
upvoted 1 times
...
sham222
1 year, 1 month ago
Selected Answer: C
The answer is C: from p 683 PMBOK 6th Ed. X5.9 PROJECT PROCUREMENT MANAGEMENT Considerations for tailoring project procurement management include but are not limited to: - Complexity of procurement. Is there one main procurement or are there multiple procurements at different times with different sellers that add to the complexity of the procurements?
upvoted 3 times
...
Zmfoutch
1 year, 4 months ago
D is correct due. Remember this process is iterative. When time to conduct procurement, the Procurement Management Plan is vital.
upvoted 1 times
...
anfacer
1 year, 6 months ago
Selected Answer: D
WPI makes more sense in Control Procurements. The question is more general so Procurement Management Plan should cover all.
upvoted 2 times
Peri_
1 year, 6 months ago
exactly
upvoted 1 times
...
...
claudiapatricia777
1 year, 7 months ago
Selected Answer: A
It is D - Procurement Plan,. It is not Work performance information because this is managed in Control Process and not in Manage Process
upvoted 1 times
...
MoonManBlue
3 years, 9 months ago
A-Work Performance Information makes the most sene, to monitor how each vendor is performing-12.3.3.2
upvoted 1 times
anfacer
1 year, 6 months ago
WPI makes more sense in Control Procurements. The question is more general so Procurement Management Plan should cover all.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...