Which of the following tasks focuses on decomposing work packages?

  • A. Adjust duration estimates
  • B. Define activities
  • C. Complete rolling wave planning
  • D. Develop milestone list
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Assad1981
7 months ago
B is correct
upvoted 1 times
...
ChymKuBoy
11 months, 2 weeks ago
Selected Answer: B
B for sure
upvoted 2 times
...
Raindrop79
1 year, 1 month ago
Pg 183 PMBOK 6th edn Define activities , the key benefit is to decompose work packages inti schedule activities
upvoted 1 times
...
MoonManBlue
3 years, 7 months ago
B-Define Activities-6.2
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago