Question #: 128
Topic #: 1
[All CAPM Questions]

At what stages of a project should the Identify Stakeholders process be performed?

  • A. When beginning each phase of the project
  • B. At the beginning of the project only
  • C. Only when the project manager is concerned about stakeholder satisfaction
  • D. When the project charter is produced, at the beginning of each phase, and when significant changes occur
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
Highly Voted 7 months, 1 week ago
Correct answer is D-at the time of the creation of the Project Charter, repeated at the start of each phase, and if a significant change in the project or organization occurs. p.508
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago