Which of the following lists represents the outputs of the Monitor Communications process?

  • A. Project communications, project management plan updates, project documents updates, and organizational process assets updates
  • B. Work performance information, change requests, project management plan updates, and project documents updates
  • C. Communications management plan, project management plan updates, work performance report, and project documents update
  • D. Stakeholder engagement plan, change requests, project management plan updates, and project documents updates
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MFrankieG2022
Highly Voted 1 year, 10 months ago
Key here is work performance information..
upvoted 6 times
...
emilianogalati
Most Recent 9 months, 1 week ago
Selected Answer: B
Chapter 10.3, pg. 392/393
upvoted 1 times
...
MoonManBlue
4 years, 1 month ago
B is correct-10.3
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago